Gap - 6 Projects Gap, Inc

Scope    New (1) Adult / Kid / Baby Format

Construction management of 8500 SF new store build-out / improvements including POG wall, display windows, fitting rooms, wood & tile floor installation and lighting.  ZWA provided: Feasibility cost / budget studies,  Lease Exhibit Negotiations with Landlord representatives, base building drawing development and coordination to meet Banana Republic brand requirements, project development / management, drawing review, bidding and contract negotiations and field supervision.

Challenges

Maintaining cost, quality and schedule in a constantly changing and demanding retail environment with numerous internal and external business partners.

Benefits to Client

ZWA’s familiarity with architectural details, brand aesthetic and constructability resulted in a cleaner project and effective resolution of issues that arose during construction. Upon competition the The client was able to experience improved asset value in the competitive retail market and better serve their ,customers.

Budget

Construction costs approx. $1,100,000

Schedule

13 weeks

 

Scope    Remodel (8 total)  Adult Format (3)  Kid / Baby Format (5)

Construction management of 4600 – 12,400SF closed store renovations including wood floor installation, cash wrap installation, display windows, POG walls, fitting rooms, entry doors / hardware, entry surround and lighting.  ZWA provided: feasibility cost / budget studies, project development / management, drawing / scope review, bidding and contract negotiation, phasing plans and coordination.

Challenges

Achieving a high level of quality and detail in an existing environment.

Benefits to Client

The clients experienced excellent communication skills, understanding of design intent, commitment to Gap brand standards and quick resolutions of problems that arose in the field due to existing conditions.

Budget

Construction costs from $46,000 - $880,000 based upon scope and size of store

Schedule

4-13 weeks pending scope

 

Scope    Temporary (2)

Construction management of 4600 – 10,000 SF brand appropriate temporary stores with services including: feasibility cost / budget studies, project development / management (schedule, consultants), drawing / scope review, bidding and contract negotiation.

Challenges

Getting a brand appropriate feel given existing conditions and a minimal budget in a short period of time while scheduling coordination with renovation.

Benefits to Client

ZWA provided an understanding of design intent resulting in a successful temporary store with minimal design documentation.  Experience with building department / code requirements minimized approval time and project managers were quick to solve problems in the field.

Budget

Construction costs from $42,000 - $65,000 based upon scope

Schedule

3-4 weeks pending scope